Nalder Hill's 3-tonne limit in Speen dates from 1978, and many SUVs and electric cars now weigh more. Officers want it scrapped; a decision is due 18 December.

The 3-tonne weight limit on Nalder Hill in Speen should be scrapped because many modern family cars are now too heavy for it, West Berkshire Council officers say.

The limit was brought in in 1978. A report for Councillor Stuart Gourley, the executive member for environment and highways, says larger SUVs, light vans and electric cars can weigh more than 3 tonnes. That makes the restriction “difficult to justify and enforce”, and potentially confusing for drivers.

Overview

  • What: the 3-tonne weight limit on Nalder Hill, Speen, would be revoked
  • In its place: advisory “Unsuitable for HGVs” signs at each end
  • Consultation: 11 responses, with 4 in favour, 4 against and 3 neutral
  • Decision date: an individual executive member decision on Friday 18 December
  • Before then: the report is down for discussion at the Highways Improvement Group on Tuesday 1 December

Why the limit is there

The report says the restriction was introduced for environmental reasons, not to protect a weak bridge or road. It helped keep lorries off Nalder Hill.

Officers now say it “no longer offers a clear or justified traffic management benefit”. They found no evidence to justify keeping it.

What people said

The council consulted by public notice, street notices and its online consultation hub. Of the 11 responses, 4 supported the change, 4 objected and 3 took no side.

The objections, as summarised in the report, were:

  • more heavy vehicles using the hill, particularly when the M4 is closed and traffic is on the A4
  • the safety of walkers on the narrow road, which links several public rights of way
  • the road itself, which is the same width and build as it was in 1978
  • the loss of a rural lane’s character

One objector asked for the road to be made a Quiet Lane. The council said that is outside the scope of this order and would need its own assessment.

Officers replied that the change is unlikely to draw lorries onto the hill. The A4 and the B4000 will remain the main routes for heavy vehicles during M4 closures, the report says. Supporters said the limit is out of date, and some said a shorter route would cut journey lengths and emissions.

What it means for you

If you drive Nalder Hill in a heavy SUV or electric car, the order would remove a limit your car may already break. Lorry drivers would still be told by the new signs that the road is unsuitable for them, but would no longer be barred.

Nothing changes until a decision is made. The report is due to be decided on 18 December, and the new signs would be paid for from the council’s minor works budget. The Highways Improvement Group discusses it first, at 6.30pm on Tuesday 1 December in the Council Chamber, Market Street (agenda).